Logo
Capitol Lake Improvement & Protection Association C.L.I.P.A.
~ Save the Lake ~
~ Preserve the Past ~
~Improve the Future ~
SaveCapitolLake.org
Logo
Friends@SaveCapitolLake.org
www.SaveCapitolLake.org
Capitol Lake Improvement & Protection Association ( C.L.I.P.A. )
mail to:  120 State Ave NE  #1006  Olympia, Wa.  98501-8212
~ Save the Lake ~ Preserve the Past ~ Improve the Future ~
Collapse <menu> Expand
Capitol Lake Reflection

CLIPA White Paper - Lake Maintenance Plan

Recommendation


The CLIPA Capitol Lake maintenance study finds that the “maintenance dredge” activity should begin immediately within the Capitol Lake North basin. A prime location for a sediment “fall-out” pocket is where the current no longer flows, which in this lake/river system is in the center of the North basin.
 
Methods
 
The maintenance dredging equipment could mobilize in the North basin at either the east edge of Marathon Park or at the extreme southwest end of Heritage Park, both of which are accessed by roadway and adjacent to the railway tracks at each end of the trestle.
(See Figure 3 – Capitol Lake Pocket Dredge - Image)
  • Alternatively, the North basin could be completely drained and allowed to sufficiently dry, such that equipment could enter the basin directly for dredging operations.
These two approaches have the following dredging spoils options:
  • A “dewatering staging area” established at the GA acreage located directly west of Marathon Park for future upland distribution;
  • Directly loaded into railway cars for overnight dewatering and haul off for landfill caps at various Pacific Northwest locations;
  • Transfer the dredging spoils into Percival Cove; or in the southwest corner of the Middle basin where prior dredging spoils were deposited; or contiguous to this area in the southern portion of the Middle basin, to begin creating a wetlands viewing park within the lake. This latter concept likely would require development of predesigned berms at strategic locations. The material would be redistributed into the Middle basin by creating wetland berms, for nature pathways, and additional park area. This set of options eliminates the need for exporting sediment, would have minimal costs, and could be accomplished within a typical “fish-window” timeframe.
 
Another option is for piping infrastructure to be installed between the North basin and lower Budd Inlet, through the dam. The North basin sediment would be pumped by tight-line to dredging barges situated in lower Budd Inlet, to be transported to another location.
(See Figure 2 – Maintenance Dredge Pipeline, Shoreline Park and Small Boat Launch - Image)
 
The pre-1986 North basin water depth was about 15 feet and is currently about 8 feet. The maintenance dredging volume to obtain the average depth of 13 to 15 feet (taking into account sloping bank contouring) is estimated to be about 100,000 cubic yards.
 

Complete White Paper PDF

Capitol Lake Improvement & Protection Association ( C.L.I.P.A. )
mail to:  120 State Ave NE  #1006  Olympia, Wa.  98501-8212
Website Design & Management by Drizzle City Design www.DrizzleCityDesign.com